How to create Start-to-Start connection between tasks?
Added by Yuriy Arseniev about 5 years ago
Dear developers,
how to create "Start-To-Start" connection between tasks?
The connection type needed if two or more tasks should start simultaneously.
---
With best regards,
Yuriy Arseniev
Replies (1)
Hello Yuriy,
a "start-to-start" relationship is currently not yet possible in OpenProject.
Depending on your situation, the use of a common preceding task and the use of "finish to start" relationship may work as a workaround:
This way, the two following tasks can be worked on as soon as the preceding task has been completed.
Best regards,
Robin